Data Centers Using Nuclear Power: One Campus With a Live Contract, 35 GW of Deals, Zero New Reactors Running
Data centers using nuclear power: as of November 2, 2026, one named US campus has a nuclear contract in force, Amazon’s site beside Pennsylvania’s Susquehanna plant. None runs on a reactor built for it. Announced deals total 34,936 MW, but 6,917 MW is output from reactors already running, and none of the other 28,019 MW is operating.
How many data centers use nuclear power?
The answer depends on the definition, and most published counts do not state one. Under the strictest useful test, a named data center with a nuclear supply contract confirmed in force in a primary document, the count is one. Talen’s August 2026 10-Q says the revised AWS contract took effect in April 2026, while its annual report expected a full front-of-the-meter transition in spring 2027. Talen also does not publish how many megawatts are flowing today, only that the schedule ramps to full volume no later than 2032.
Meta could become the second. Vistra anticipated first deliveries from Perry and Davis-Besse in late 2026, but its latest 10-Q, filed August 10, does not confirm a start, so we do not count it. In the binding documents we read, the only sites named below state level are the Susquehanna campus and Google’s Montgomery County, Tennessee, and Jackson County, Alabama, data centers, which Hermes 2 will serve through TVA from 2030. Any data center on a grid with reactors also draws some nuclear electricity, which cannot be counted from public data. For where US data centers sit, see our data centers by state atlas.
Do data centers have nuclear reactors?
Not today, in any US project we could document. Amazon bought the Susquehanna campus and related assets for $650 million in March 2024, but Talen runs the plant next door, and the deal was restructured to flow across the grid. Aalo says it will power a Crusoe modular data center in 2027 as a proof of concept, and describes that as the first of its kind, which supports the zero. Fermi has proposed four AP1000 units on its Amarillo campus, but its NRC page shows the third part of the application targeted for December 31, 2026, and every safety review date as TBD.
How many data centers can a nuclear power plant handle?
Campus sizes are rarely disclosed, so this table uses one that is: Fermi’s TensorWave lease, 222 MW of facility power with an option to reach 650 MW. We assume the campus runs at full load and each plant at the 91.1% capacity factor EIA reports for the US fleet in 2025. By that math Crane covers about 3.4 campuses of 222 MW, or 1.2 at 650 MW. Lawrence Berkeley National Laboratory’s 176 TWh for all US data centers in 2023 equals about 20.1 GW of average load, which would take about 26 Cranes.
| Plant or contract | MW | Average MW at 91.1% | 222 MW campuses | 650 MW campuses | Share of 2023 US data center load |
|---|---|---|---|---|---|
| Hermes 2 source | 50 | 46 | 0.2 | 0.1 | 0.2% |
| Four Xe-100 units (Cascade first phase) source | 320 | 292 | 1.3 | 0.4 | 1.5% |
| One Natrium unit source | 345 | 314 | 1.4 | 0.5 | 1.6% |
| Duane Arnold source | 615 | 560 | 2.5 | 0.9 | 2.8% |
| Crane source | 835 | 761 | 3.4 | 1.2 | 3.8% |
| First AP1000 at Project Matador source | 1,000 | 911 | 4.1 | 1.4 | 4.5% |
| Clinton source | 1,121 | 1,021 | 4.6 | 1.6 | 5.1% |
| Susquehanna contract at full volume source | 1,920 | 1,749 | 7.9 | 2.7 | 8.7% |
Our arithmetic from cited MW. Applying a fleet capacity factor to unbuilt designs is an assumption. One lease is an example, not an industry average.
What changed most recently
The past five weeks moved money and paper, not electrons. Amazon and Google signed 1,080 MW of uprates at Constellation between September 30 and October 6, DOE offered conditional commitments of up to $9.2 billion across Vistra and Constellation, and Amazon added a 960 MW Indiana feasibility project. At Palisades, the plant setting the pace for restarts, the NRC issued an exigent amendment on October 13 so Holtec can recover a tilted fuel assembly.
| Date | Event | Document |
|---|---|---|
| Oct 27, 2026 | DOE conditional loan commitment of up to $5 billion for Constellation uprates at eight plants. Not a final decision on any uprate. | Constellation, Oct 27, 2026 |
| Oct 19, 2026 | X-energy and AEP sign a Joint Development Agreement for 960 MW in Sullivan County, Indiana; Amazon funds development. | X-energy, Oct 2026 |
| Oct 13, 2026 | NRC issues Amendment 283 so Holtec can move tilted fuel assembly DD41 at Palisades, and issues a chilled-work-environment letter the same day. | NRC Palisades page |
| Oct 9, 2026 | NRC publishes Fermi’s draft EIS (91 FR 64702). Comments close Nov 23, 2026. | 91 FR 64702 |
| Oct 6, 2026 | Google and Constellation: 20-year PPA for 890 MW of uprates at 11 units, plus a separate 15-year, 2,700 MW supply deal. | Constellation, Oct 2026 |
| Oct 5, 2026 | DOE conditional loan commitment of up to $4.2 billion for Vistra uprates and modernization. | DOE, Oct 2026 |
| Oct 2, 2026 | Oracle commits to subscribe to part of Point Beach’s output, subject to Wisconsin PSC approval. | Oracle, Oct 2026 |
| Sep 30, 2026 | Amazon and Constellation: 20-year agreement for 690 MW at Calvert Cliffs, including a 190 MW uprate. | Constellation, Sep 2026 |
| Sep 21, 2026 | Google and Georgia Power file the NU-1 uprate tariff for about 96 MW at Vogtle and Hatch. | Georgia Power, Sep 2026 |
| Sep 18, 2026 | NRC issues the final EA and FONSI for the Crane restart (ML26231A018). | NRC Crane page |
| Sep 8, 2026 | DOE closes a loan of up to $1.9 billion for Duane Arnold. | NextEra, Sep 2026 |
| Aug 9, 2026 | Fermi signs TensorWave, its first campus lease, at 222 MW of facility power. | Fermi 10-Q, Q2 2026 |
| Jul 30, 2026 | Crusoe and Aalo announce a partnership; proof of concept in 2027. NRC issues the Duane Arnold draft EA the same day. | Aalo, Jul 2026 |
| Jul 1, 2026 | NRC Amendment 307 lets Crane receive new fuel. It does not allow fuel in the reactor. | NRC Amendment 307 |
| Jun 18, 2026 | FERC order 195 FERC 61,209 on rehearing and compliance in the PJM co-location case. | 195 FERC 61,209 |
| May 18, 2026 | NRC completes the EA and FONSI for Dow’s Long Mott Xe-100 plant, the reference project for Amazon’s X-energy deals. | NRC Long Mott log |
| Apr 23, 2026 | TerraPower starts construction on Kemmerer 1, the reference plant for Meta’s Natrium deal. | TerraPower, Apr 2026 |
| Apr 17, 2026 | Kairos breaks ground on Hermes 2. | Kairos, Apr 2026 |
| Mar 9, 2026 | NRC issues construction permit CPAR-1 for Kemmerer 1. | NRC CPAR-1 notice |
| Jan 9, 2026 | Meta announces Vistra, TerraPower and Oklo agreements totaling up to 6.6 GW. | Meta, Jan 2026 |
| Dec 18, 2025 | FERC finds PJM’s tariff unjust and unreasonable on co-located load (EL25-49). | 195 FERC 61,209 |
| Dec 16, 2025 | NRC renews Clinton’s license for 20 years. | Constellation, Dec 2025 |
| Jun 11, 2025 | Talen and Amazon replace the co-located deal with a 1,920 MW front-of-the-meter PPA through 2042. | Talen 8-K, Jun 2025 |
| Nov 1, 2024 | FERC rejects the Susquehanna amended ISA (189 FERC 61,078), which would have raised co-located load from 300 MW to 480 MW. | 189 FERC 61,078 |
| Sep 20, 2024 | Microsoft and Constellation sign the 20-year Crane PPA. | Constellation, Sep 2024 |
Every project, by NRC stage
Megawatts tied to data center deals, by where each sits in the licensing process
Existing reactor outputRestartUprateNew reactor
Bar lengths share one scale. Stage reflects NRC project pages and filings read November 2, 2026. Hover a segment for the deal.
Only 6,450 MW is under active NRC review, and 5,000 MW of that is Fermi’s application, which is not yet complete. The largest group, 19,510 MW, has no application and no filing date, and 12,000 MW of it is one framework with Switch. The one project holding a construction permit is 50 MW.
The tracker
| Buyer, seller | Reactor or site | MW | Type | NRC docket | NRC status | What remains | Target as stated | Documents |
|---|---|---|---|---|---|---|---|---|
| MetaVistra | Perry and Davis-Besse, OH | 2,176 | Existing reactor outputBinding contract | 05000440, 05000346 |
Perry renewed to 2046 (Vistra 10-Q). Davis-Besse license ends Apr 22, 2037, inside the 20-year PPA. | Davis-Besse needs a further renewal to cover the PPA term. | Portion in late 2026; full delivery by year end 2027 | Vistra 8-K, Jan 2026 · Vistra 10-Q, Q2 2026 · NRC Davis-Besse |
| Amazon (AWS)Talen | Susquehanna 1 and 2, PA | 1,920 | Existing reactor outputBinding contract | 05000387, 05000388 |
Renewed licenses run to Jul 17, 2042 and Mar 23, 2044. Contract in force: Talen says the transition to the revised PPA occurred in April 2026. | Nothing at NRC. Ramp continues; Talen publishes no current delivered MW in the filings we read. | Up to 1,920 MW through 2042; full volume no later than 2032 | Talen 10-Q, Q2 2026 · Talen 8-K, Jun 2025 · Talen 2025 annual report · NRC Susquehanna 1 |
| Amazon (AWS)Vistra | Comanche Peak 1 and 2, TX | 1,200 | Existing reactor outputBinding contract | 05000445, 05000446 |
Licenses run to Feb 8, 2050 and Feb 2, 2053. | Nothing at NRC. Delivery has not started on Vistra’s stated schedule. | Delivery begins Q4 2027; full capacity by 2032 | Vistra 10-Q, Q2 2026 · NRC Comanche Peak 1 · NRC Comanche Peak 2 |
| MetaConstellation | Clinton, IL | 1,121 | Existing reactor outputBinding contract | 05000461 |
NRC renewed the license Dec 16, 2025, to Apr 17, 2047. | Nothing for the sale. Subsequent renewal application planned for Q2 2028. | 20-year PPA begins June 2027 | Constellation, Jun 2025 · Constellation, Dec 2025 · Constellation letter to NRC, Oct 2026 |
| AmazonConstellation | Calvert Cliffs 1 and 2, MD (existing share) | 500 | Existing reactor outputBinding contract | 05000317, 05000318 |
Licenses end Jul 31, 2034 and Aug 13, 2036, inside the 20-year term. | Relicensing for 20 more years, which Constellation says the deal supports. | 20-year term; start date not stated. 690 MW less the 190 MW uprate | Constellation, Sep 2026 · NRC Calvert Cliffs 1 · NRC Calvert Cliffs 2 |
| MicrosoftConstellation | Crane Clean Energy Center (Three Mile Island Unit 1), PA | 835 | RestartBinding contract | 05000289 |
Exemption plus three license amendments under review; none shows final documentation. Final EA and FONSI Sep 18, 2026. Fuel receipt allowed by Amendment 307, Jul 1, 2026. | NRC decisions expected by Mar 4, 2027; open RAIs from Sep 2026; FEMA review and full-participation emergency exercise; operational readiness inspections. | Restart in 2027 | NRC Crane page · NRC schedule letter, ML25345A027 · Constellation Q2 2026 results · Constellation 10-Q, Q2 2026 · Constellation, Sep 2024 |
| Google (50 MW to CIPCO)NextEra | Duane Arnold, IA | 615 | RestartBinding contract | 05000331 |
Exemption plus three license amendments under review. Draft EA and FONSI Jul 30, 2026; final projected Fall 2026. Hearing petition filed Jun 22, 2026. | NRC decisions expected by Jan 29, 2028; restart inspections; subsequent renewal because the license ends Feb 21, 2034. | No later than Q1 2029, perhaps Q4 2028 | NRC Duane Arnold page · NRC schedule letter, ML26082A006 · Duane Arnold hearing petition, ML26173A206 · NextEra 8-K, Oct 2025 · NextEra, Sep 2026 |
| GoogleConstellation | 11 units at six plants in IL, PA, NJ (units not named) | 890 | UprateBinding contract | Withheld (NRC lists plant as Proprietary) |
Not under review: NRC lists no pending uprate applications. Constellation’s first planned extended uprate filing is Q4 2026. | Uprate license filings, engineering, outages. DOE loan commitment of up to $5B is conditional. | First uprate by 2028; end date not stated | Constellation, Oct 2026 · Google, Oct 2026 · NRC pending uprates · NRC expected uprates · Constellation, Oct 27, 2026 |
| MetaVistra | Perry, Davis-Besse, Beaver Valley 1 and 2 | 433 | UprateBinding contract | 05000440, 05000346, 05000334, 05000412 |
Not under review. NRC lists planned filings: Perry Q3 2029, Beaver Valley 2 Q3 2030, Beaver Valley 1 Q3 2031, Davis-Besse Q3 2032. | Those filings and approvals. DOE loan of up to $4.2B is conditional. Under 20% of spend projected by year end 2028. | First delivery by 2031; all by year end 2034 | Vistra 8-K, Jan 2026 · NRC expected uprates · DOE, Oct 2026 |
| AmazonConstellation | Calvert Cliffs 1 and 2, MD | 190 | UprateBinding contract | 05000317, 05000318 |
Not under review. NRC’s list withholds Constellation plant names. | Uprate filing and approval, plus relicensing. | Between 2030 and 2032 | Constellation, Sep 2026 · NRC expected uprates |
| Google (credits only)Georgia Power | Vogtle 1 and 2, Hatch 1 and 2, GA | 96 | UprateBinding contract | 05000424, 05000425, 05000321, 05000366 |
Not under review. NRC lists planned filings: Hatch Q2 2027, Vogtle Q4 2028. Filed at Georgia PSC Sep 21, 2026 (Dockets 44280, 56002). | NRC filings. Georgia Power’s release says PSC approval was required; Data Center Frontier reports approval in October, and we did not read the order. | No date stated | Georgia Power, Sep 2026 · NRC expected uprates · Data Center Frontier · NRC Hatch 1 · NRC Vogtle 1 |
| MetaConstellation | Clinton, IL (uprate) | 30 | UprateBinding contract | 05000461 |
Not under review. | Any license filing the work requires. | No date stated | Constellation, Jun 2025 · Constellation, Oct 27, 2026 |
| SwitchOklo | Sites not named | 12,000 | New reactorNon-binding framework | None |
12 GW Master Power Agreement, Dec 2024. Oklo’s Aug 2026 10-Q lists Switch among prospective customers. | Binding contracts, sites, licenses, and a first Aurora powerhouse. | Through 2044 (announcement excerpt) | Oklo 10-Q, Q2 2026 · Oklo 10-K, FY2024 |
| Fermi (own campus)Westinghouse AP1000 | Project Matador, Amarillo, TX (4 units) | 5,000 | New reactorDevelopment stage | 05200051 to 05200054 |
Parts 1 and 2 accepted Sep 5, 2025. Part 3 targeted Dec 31, 2026. Safety review dates TBD. Draft EIS comments close Nov 23, 2026. | Part 3, full review schedule, combined licenses, construction contracts. First tenant lease (222 MW) is planned on other power first. | No year stated in filings we read | NRC Fermi page · 91 FR 64702 · Fermi 10-K, FY2025 · Fermi 10-Q, Q2 2026 |
| MetaTerraPower | Up to 8 Natrium units, site not named | 2,800 | New reactorDevelopment stage | None |
No site named. Reference plant Kemmerer 1 holds permit CPAR-1 (Mar 9, 2026) and began construction Apr 23, 2026. | Site, permit, operating license. Kemmerer itself still needs a separate operating license. | First two units (690 MW) as early as 2032; rest by 2035 | Meta, Jan 2026 · TerraPower, Jan 2026 · NRC 26-028 · NRC CPAR-1 notice · TerraPower, Apr 2026 |
| Google (option)Elementl Power | Three potential sites, not named | 1,800 | New reactorDevelopment stage | None |
Early-stage capital, each site aiming for at least 600 MW. Google holds an option on off-take. | Sites, technology, permits, and Google’s off-take decision. | Elementl goal: online by 2035 | Google, May 2025 |
| MetaOklo | Pike County, OH | 1,200 | New reactorDevelopment stage | None |
Prepayment agreement Jan 5, 2026. No application: Oklo says it is evaluating the timing and form of future NRC applications. | License or authorization route, fuel, construction. NRC denied Oklo’s earlier application Jan 6, 2022, without prejudice. | As early as 2030 | Oklo 10-Q, Q2 2026 · Meta, Jan 2026 · NRC Oklo page |
| AmazonAEP, X-energy | Near former Breed station, Sullivan County, IN | 960 | New reactorDevelopment stage | None |
Joint Development Agreement announced Oct 19, 2026 to advance feasibility work. | Feasibility, further agreements, permit, operating license. | No date stated | X-energy, Oct 2026 · Amazon, Oct 2026 |
| GoogleKairos Power | Fleet, sites not named (500 MW less Hermes 2) | 450 | New reactorDevelopment stage | None |
No application found for later units. | Sites, permits, operating licenses, and a working Hermes 2. | By 2035 | Kairos and Google · Kairos, Aug 2025 |
| AmazonEnergy Northwest, X-energy | Cascade, central WA (first 4 units) | 320 | New reactorDevelopment stage | None yet |
Construction permit application targeted by end of 2026. Reference plant Long Mott (Dow) had its EA and FONSI May 18, 2026. | Application; permit anticipated in 2028; construction; operating license. Option to upsize to 960 MW is not counted. | Early 2030s | X-energy 10-Q, Q2 2026 · X-energy prospectus · NRC Long Mott log |
| AmazonDominion | Near North Anna, VA | 300 | New reactorDevelopment stage | None |
Agreement to explore an SMR, signed 2024. | Everything: Amazon describes exploring development. | No date stated | Amazon, Oct 2024 · Amazon carbon-free energy page |
| Google (via TVA)Kairos Power | Hermes 2, Oak Ridge, TN | 50 | New reactorBinding contract | 05000611, 05000612 |
Construction permits issued Nov 21, 2024. Ground broken Apr 17, 2026. NRC’s page describes two 35 MWt test reactors; Kairos now plans one reactor at 50 MW. | Operating license. The documents we read do not say whether the redesign needs a permit change. | Operations in 2030 | NRC Hermes 2 page · Kairos, Aug 2025 · Kairos, Apr 2026 · TVA 10-K, FY2025 · Google, Aug 2025 |
| CrusoeAalo Atomics | Crusoe sites, not named (first demo in 2027) | 50 | New reactorDevelopment stage | None |
Partnership Jul 30, 2026. Aalo’s test reactor reached criticality Jul 4, 2026 under the DOE pilot program. | A power-producing reactor, then the 50 MWe plant. | Proof of concept 2027; 50 MWe plants by end of 2029 | Aalo, Jul 2026 · POWER magazine |
| Total announced | 34,936 | Of which 6,917 existing output, 1,450 restart, 1,639 uprate, 24,930 new reactors. Operating new capacity: 0. | ||||||
Duane Arnold’s 615 MW includes 50 MW for CIPCO; NextEra does not state Google’s share separately. Kairos’s 500 MW fleet is split into Hermes 2 and the remaining 450 MW so it is not double counted. Fermi’s 5,000 MW is its 1 GW first unit plus up to 4.0 GW for Units 2 to 4; its 10-K also cites 6.0 GW with later SMRs, not counted.
By type
| Existing reactor output | 6,917 | 19.8% |
| Restart | 1,450 | 4.2% |
| Uprate | 1,639 | 4.7% |
| New reactor | 24,930 | 71.4% |
By firmness
| Binding contract | 10,056 | 28.8% |
| Development stage | 12,880 | 36.9% |
| Non-binding framework | 12,000 | 34.3% |
By reactor
| Existing reactors (running or restarting) | 10,006 | 28.6% |
| Designs with no commercial unit operating | 17,830 | 51.0% |
| Built design (AP1000) | 5,000 | 14.3% |
| Technology not chosen | 2,100 | 6.0% |
Existing, restarting and uprated reactors account for 10,006 MW, 29% of the total, and nearly all of the 10,056 MW under binding contract. Designs with no commercial unit operating account for 17,830 MW, and two-thirds of that is the Switch framework. Meta’s up to 6.6 GW, Google’s over 1.5 GW and Constellation’s approximately 1,080 MW all reconcile with these rows.
Named, but not in the totals
| Arrangement | MW | Why it is out | Documents |
|---|---|---|---|
| Google and Constellation, 15-year supply | 2,700 MW | Release says “PJM’s fleet” and “operating generation assets” without a nuclear split, and Constellation also owns gas plants. Data Center Frontier calls it nuclear; the primary release does not. | Constellation, Oct 2026 · Data Center Frontier |
| Oracle and We Energies, Point Beach | 125 to 250 MW (WPR) | Subject to Wisconsin PSC approval; Oracle’s and We Energies’ releases give no MW. Licenses end Oct 5, 2030 and Mar 8, 2033. | Oracle, Oct 2026 · We Energies, Oct 2026 · WPR · NRC Point Beach 1 · NRC Point Beach 2 |
| Palisades restart, Holtec | About 800 MW | PPAs are with Wolverine Power Cooperative and Hoosier Energy, not a data center operator. | Holtec S-1 · NRC Palisades page |
| Equinix and Oklo | Not stated in filing | Oklo’s 10-Q calls it a non-binding letter of intent and gives no MW in the passage we read. | Oklo 10-Q, Q2 2026 · Oklo 10-K, FY2024 |
| Prometheus Hyperscale and Oklo | Not stated in filing | Non-binding letter of intent. | Oklo 10-Q, Q2 2026 |
| Walmart and Constellation, Dresden | About 176 MW (trade press) | The buyer is a distribution center, not a data center. | Data Center Frontier |
Trackers also list Crusoe and Blue Energy (Port of Victoria, TX), Equinix and Radiant, NuScale and Standard Power, Deep Fission and Endeavour, Sabey and TerraPower, GridMarket and Deployable Energy, and Last Energy in Texas. We did not read a primary document for these in this update, so they are not counted or described here.
What remains before each type can start
Restarts: 1,450 MW, and the Palisades warning
Crane and Duane Arnold each need an exemption from 10 CFR 50.82 and three license amendments, covering the license and technical specifications, the security plan, and the emergency plan. The NRC page for Crane, last updated October 8, shows final documentation blank on all four, with additional-information requests issued September 18 and 25. Staff expects decisions by March 4, 2027, and by January 29, 2028 for Duane Arnold. Each review is budgeted at about 5,540 staff and contractor hours. Crane also needs FEMA review and a full-participation emergency exercise, and PJM’s study found contingent transmission upgrades with dates as late as December 2030. FERC granted a waiver in June 2026 that Constellation filed to reduce them.
Uprates: 1,639 MW, none filed
The NRC’s pending uprates page, updated September 15, 2026, says there are no applications under review. Its expected list shows 31 units and about 2,421 MWe through 2032, with Constellation’s plant names withheld and its first extended uprate filing due in Q4 2026. These deals equal 68% of that expected total, and 20% of the 8 GWe from all 172 uprates approved since 1977. Constellation describes its work as raising “thermal and electrical efficiency”, and no document splits how many MW need a license amendment, so some may not pass through this queue.
New reactors: 24,930 MW, one permit
Hermes 2 is the only data-center-linked reactor with a construction permit. That page, updated October 29, still describes two 35 MWt test reactors, while Kairos now plans one reactor at 50 MW. Meta’s Natrium units and Amazon’s Xe-100 units depend on reference plants that are themselves unfinished: Kemmerer 1 holds a permit but needs a separate operating license, and X-energy expects Long Mott’s permit in the first quarter of 2027. Oklo says it is evaluating the timing and form of future NRC applications while pursuing DOE authorization in Idaho.
Licenses that end before the contracts do
Restarting a plant does not extend its license. Crane’s ends in 2034, about seven years into a 20-year PPA, and Duane Arnold’s ends in 2034, about five years into a 25-year PPA. Of the 8 reactor sites below, at least 4 need a further renewal to reach the end of their contract, and Perry would fall about a year short on our estimate.
| Plant | Contract | Contract end (our estimate) | NRC license expires | Next step |
|---|---|---|---|---|
| Crane | 20-year PPA from 2027 | About 2047 | Apr 19, 2034 | Second renewal application planned Q1 2029 (source) |
| Duane Arnold | 25-year PPA from about 2029 | About 2054 | Feb 21, 2034 | Notice of intent to seek subsequent renewal, Jan 23, 2025 (source) |
| Calvert Cliffs | 20-year agreement, start not stated | Not stated | Jul 31, 2034; Aug 13, 2036 | Constellation says the deal supports relicensing for 20 years (source) |
| Davis-Besse | 20-year PPA from late 2026 to 2027 | About 2047 | Apr 22, 2037 | DOE says the investments support 20 more years of operation (source) |
| Perry | 20-year PPA from late 2026 to 2027 | About 2047 | 2046 (Vistra 10-Q) | Renewal approved Jul 2025. NRC’s page still shows Nov 7, 2026 (source) |
| Clinton | 20-year PPA from June 2027 | About 2047 | Apr 17, 2047 | Subsequent renewal application planned Q2 2028 (source) |
| Susquehanna | PPA through 2042 | 2042 | Jul 17, 2042; Mar 23, 2044 | Covered (source) |
| Comanche Peak | 20-year PPA from Q4 2027 | About 2047 | Feb 8, 2050; Feb 2, 2053 | Covered (source) |
The Susquehanna lesson at FERC
The first deal shows how the contract form changed. On November 1, 2024, FERC rejected an amended agreement that would have raised co-located load at Susquehanna from 300 MW to 480 MW. In June 2025, Talen and Amazon replaced it with a larger 1,920 MW front-of-the-meter PPA, which moves the load onto the grid, and Talen dropped its appeal in January 2026. On December 18, 2025, FERC found PJM’s tariff unjust and unreasonable on co-located load, and it issued a further order on June 18, 2026.
Stated target dates by year
When new capacity is promised, from the earliest date each owner states
RestartUprateNew reactor. Faded bars have no stated end date.
| Earliest stated year | Projects, MW | MW | Cumulative MW | TWh a year at 91.1% |
|---|---|---|---|---|
| 2027 | Crane, 835 | 835 | 835 | 6.7 |
| 2028 | Google and Constellation uprates (only the first is dated), 890 | 890 | 1,725 | 13.8 |
| 2029 | Duane Arnold, 615; Crusoe and Aalo, 50 | 665 | 2,390 | 19.1 |
| 2030 | Hermes 2, 50; Meta and Oklo, Pike County, 1,200; Calvert Cliffs uprate (2030 to 2032), 190 | 1,440 | 3,830 | 30.6 |
| 2031 | Vistra uprates (2031 to 2034), 433; Cascade (“early 2030s”), 320 | 753 | 4,583 | 36.6 |
| 2032 | First two Natrium units, 690 | 690 | 5,273 | 42.1 |
| 2035 | Other Natrium units, 2,110; Kairos fleet, 450; Elementl sites, 1,800 | 4,360 | 9,633 | 76.9 |
| 2044 | Switch and Oklo, 12,000 | 12,000 | 21,633 | 172.6 |
| No date | Vogtle 1 and 2, 96; Clinton, 30; Near former Breed station, 960; Near North Anna, 300; Project Matador, 5,000 | 6,386 | 28,019 |
Best case by construction. Only the first Google uprate is dated, and we place all 890 MW in 2028. Cascade’s “early 2030s” is placed in 2031. These are targets, not forecasts.
How that compares with data center load growth
LBNL’s report to Congress puts US data center electricity at 176 TWh in 2023 and 325 to 580 TWh in 2028, a rise of 149 to 404 TWh. Crane alone would produce about 6.7 TWh a year. Even with every Google uprate by 2028, the best case of 1,725 MW produces 13.8 TWh, which is 3.4% to 9.2% of that rise. Output from all 6,917 MW of existing reactors, about 55 TWh, is larger but already on the grid, and equals 7.0% of the 98.4 GW US fleet in EIA’s 2025 table.
Terawatt-hours a year: nuclear deals against projected load growth
Deal figures: MW times 8,760 hours times EIA’s 91.1% 2025 nuclear capacity factor. The 2030 bar falls after LBNL’s 2028 endpoint, so it flatters the comparison.
Federal loans behind the projects
| Project | DOE amount | Status | Document |
|---|---|---|---|
| Crane | Up to $1.0B | Closed Nov 2025; no borrowings as of the Aug 2026 10-Q | Constellation 10-Q, Q2 2026 |
| Duane Arnold | Up to $1.9B | Financial close Sep 2026 | NextEra, Sep 2026 |
| Palisades (no data center buyer) | Up to $1.52B | Loan guarantee facility | Holtec S-1 |
| Vistra uprates | Up to $4.2B | Conditional, Oct 5, 2026 | DOE, Oct 2026 |
| Constellation uprates | Up to $5.0B | Conditional, Oct 27, 2026 | Constellation, Oct 27, 2026 |
What this means for MSPs
Do not plan around this power before 2030. A three-year client contract signed today ends in late 2029, when the best case is 2,390 MW of new nuclear, against LBNL’s projected rise of 149 to 404 TWh by 2028. Capacity and price planning belongs with the numbers in our AI energy consumption ledger and our data center electricity prices test, not with this tracker.
Question any “nuclear-powered” claim. If a colocation or cloud vendor uses the phrase, ask for the plant, the MW, the contract start date and the NRC docket. Six of the binding lines reassign output from reactors already running, or add credits, as Google’s Georgia Power tariff does, and neither puts a reactor behind your client’s rack.
Do not pick a region for this. With one named campus and contracts written at PJM or state level, no public document lets a client buy nuclear by choosing a cloud region. Clients with reporting duties should use the provider’s published figures, and our data center statistics cover the wider load picture.
If a client asks, these dated checkpoints will show whether the schedule holds:
- Nov 23, 2026Fermi draft EIS comments close
- Q4 2026Constellation’s first extended uprate filing, per the NRC list
- Dec 31, 2026Fermi’s application Part 3 target; X-energy’s Cascade permit filing target by year end
- Q1 2027X-energy’s expected Long Mott permit
- Mar 4, 2027NRC decisions on Crane
- Mar 2027Holtec’s commitment date to its Palisades buyers
- Jan 29, 2028NRC decisions on Duane Arnold
Frequently asked questions
How many data centers use nuclear power?
One named US campus has a nuclear supply contract in force as of November 2, 2026: Amazon’s campus beside the Susquehanna plant in Pennsylvania, under a Talen contract of up to 1,920 MW. Beyond that, 12 other binding contract lines with 4 buyers are signed but start later, and most name a region, not a building. Any data center on a grid with reactors draws some nuclear electricity, which cannot be counted.
Do data centers have nuclear reactors?
No data center in our tracker has a reactor on site powering it today. The closest plans are Aalo’s proof of concept with a Crusoe modular data center in 2027 and four AP1000 units proposed at Fermi’s Project Matador campus, whose combined license review has no safety schedule yet. Amazon’s Susquehanna campus sits next to a reactor plant it does not own.
How many data centers can a nuclear power plant handle?
Using one disclosed campus size, Fermi’s 222 MW TensorWave lease, Crane’s 835 MW at the 91.1% fleet capacity factor covers about 3.4 such campuses, or 1.2 campuses at the 650 MW expansion size. Crane’s output equals about 3.8% of all US data center electricity use in 2023, so about 26 Cranes would be needed to match that year.
Which companies have nuclear deals for data centers?
Amazon, Meta, Google and Microsoft hold the 13 binding contract lines we counted, totaling 10,056 MW. Crusoe, Fermi and Switch appear in development-stage or non-binding arrangements. Meta’s own total of up to 6.6 GW reconciles with its 2,609 MW from Vistra, 1,200 MW from Oklo and 2,800 MW from TerraPower.
Is Three Mile Island back online for Microsoft?
No. Unit 1, now the Crane Clean Energy Center, remains in decommissioned status. The NRC expects final decisions on its exemption and three license amendments by March 4, 2027, and Constellation states a 2027 restart. NRC Amendment 307 of July 1, 2026 only lets the plant receive new fuel.
When will small modular reactors power data centers?
The earliest firm-contract date is 2030, for Kairos Power’s 50 MW Hermes 2 plant, which holds a construction permit but has no operating license. Aalo and Crusoe plan a 2027 proof of concept and 50 MWe plants by the end of 2029 under a separate path. X-energy expects Amazon-backed reactors in the early 2030s.
Methodology
Sources and retrieval. We downloaded NRC project pages, schedule letters and Federal Register notices, FERC orders, SEC filings (Constellation, Talen, Vistra, Oklo, NextEra, X-energy, Fermi, Holtec, TVA, WEC), DOE releases and company announcements on November 2, 2026, and read each deal from them. NRC pages carry their own update dates, which we cite where they matter. A build script checks 152 quoted passages against 74 saved documents, so the tracker can be rerun as filings change.
Definitions. “Contract in force” means a primary document says the contract has taken effect. Scope is US fission projects with a named data center operator or hyperscaler as counterparty or beneficiary and a stated MW. “Binding contract” covers PPAs and tariff subscriptions; some remain subject to regulatory approval or conditions. “Development stage” covers funding, prepayment, feasibility and self-developed projects. MW are nameplate or contract figures as stated, many of them “up to”. “No application found” means none appears on the NRC pages and filings we read, not a search of every ADAMS record.
Limits. Non-US deals and fusion are out of scope. Talen does not disclose current deliveries, and buyers do not disclose which buildings use the power, so a true building count is not possible. Contract end dates are our estimates from stated start dates and terms. Oklo’s Switch agreement was read in Oklo’s filings; the “non-binding” wording and the 2044 end date come from a search excerpt of the announcement because the page blocked our download. Projects with no primary document in hand are listed as unverified, not assessed. Capacity factors for unbuilt designs are assumptions.
Not advice. This is an analysis of public documents, not investment, legal or procurement advice.
Cite as:The Uptime Report. "Data Centers Using Nuclear Power: One Campus With a Live Contract, 35 GW of Deals, Zero New Reactors Running." November 2026. https://theuptimereport.com/data-centers-using-nuclear-power/
References
- Talen 10-Q, Q2 2026. Accessed November 2026.
- Talen 8-K, Jun 2025. Accessed November 2026.
- Talen 2025 annual report. Accessed November 2026.
- NRC Susquehanna 1. Accessed November 2026.
- Vistra 10-Q, Q2 2026. Accessed November 2026.
- NRC Comanche Peak 1. Accessed November 2026.
- NRC Comanche Peak 2. Accessed November 2026.
- Vistra 8-K, Jan 2026. Accessed November 2026.
- NRC Davis-Besse. Accessed November 2026.
- Constellation, Jun 2025. Accessed November 2026.
- Constellation, Dec 2025. Accessed November 2026.
- Constellation letter to NRC, Oct 2026. Accessed November 2026.
- Constellation, Sep 2026. Accessed November 2026.
- NRC Calvert Cliffs 1. Accessed November 2026.
- NRC Calvert Cliffs 2. Accessed November 2026.
- NRC Crane page. Accessed November 2026.
- NRC schedule letter, ML25345A027. Accessed November 2026.
- Constellation Q2 2026 results. Accessed November 2026.
- Constellation 10-Q, Q2 2026. Accessed November 2026.
- Constellation, Sep 2024. Accessed November 2026.
- NRC Duane Arnold page. Accessed November 2026.
- NRC schedule letter, ML26082A006. Accessed November 2026.
- Duane Arnold hearing petition, ML26173A206. Accessed November 2026.
- NextEra 8-K, Oct 2025. Accessed November 2026.
- NextEra, Sep 2026. Accessed November 2026.
- Constellation, Oct 2026. Accessed November 2026.
- Google, Oct 2026. Accessed November 2026.
- NRC pending uprates. Accessed November 2026.
- NRC expected uprates. Accessed November 2026.
- Constellation, Oct 27, 2026. Accessed November 2026.
- DOE, Oct 2026. Accessed November 2026.
- Georgia Power, Sep 2026. Accessed November 2026.
- Data Center Frontier. Accessed November 2026.
- NRC Hatch 1. Accessed November 2026.
- NRC Vogtle 1. Accessed November 2026.
- NRC Hermes 2 page. Accessed November 2026.
- Kairos, Aug 2025. Accessed November 2026.
- Kairos, Apr 2026. Accessed November 2026.
- TVA 10-K, FY2025. Accessed November 2026.
- Google, Aug 2025. Accessed November 2026.
- Kairos and Google. Accessed November 2026.
- Oklo 10-Q, Q2 2026. Accessed November 2026.
- Meta, Jan 2026. Accessed November 2026.
- NRC Oklo page. Accessed November 2026.
- TerraPower, Jan 2026. Accessed November 2026.
- NRC 26-028. Accessed November 2026.
- NRC CPAR-1 notice. Accessed November 2026.
- TerraPower, Apr 2026. Accessed November 2026.
- X-energy 10-Q, Q2 2026. Accessed November 2026.
- X-energy prospectus. Accessed November 2026.
- NRC Long Mott log. Accessed November 2026.
- X-energy, Oct 2026. Accessed November 2026.
- Amazon, Oct 2026. Accessed November 2026.
- Amazon, Oct 2024. Accessed November 2026.
- Amazon carbon-free energy page. Accessed November 2026.
- Google, May 2025. Accessed November 2026.
- Aalo, Jul 2026. Accessed November 2026.
- POWER magazine. Accessed November 2026.
- NRC Fermi page. Accessed November 2026.
- 91 FR 64702. Accessed November 2026.
- Fermi 10-K, FY2025. Accessed November 2026.
- Fermi 10-Q, Q2 2026. Accessed November 2026.
- Oklo 10-K, FY2024. Accessed November 2026.
- Oracle, Oct 2026. Accessed November 2026.
- We Energies, Oct 2026. Accessed November 2026.
- WPR. Accessed November 2026.
- NRC Point Beach 1. Accessed November 2026.
- NRC Point Beach 2. Accessed November 2026.
- Holtec S-1. Accessed November 2026.
- NRC Palisades page. Accessed November 2026.
- NRC Amendment 307. Accessed November 2026.
- 195 FERC 61,209. Accessed November 2026.
- 189 FERC 61,078. Accessed November 2026.
- NRC, RIC 2026 session abstract on power uprates. Accessed November 2026.
- EIA Electric Power Monthly, Table 6.07.B, capacity factors. Accessed November 2026.
- NRC public meeting slides on Crane, Jul 28, 2026 (ML26204A045). Accessed November 2026.
- NRC, Palisades Amendment 283 (ML26282A040). Accessed November 2026.
- Palisades Energy license amendment request, Sep 30, 2026 (ML26273A469). Accessed November 2026.
- DOE, Crane loan announcement. Accessed November 2026.
- WEC Energy 8-K, Aug 14, 2026. Accessed November 2026.
- NRC Kemmerer application page. Accessed November 2026.
- NRC Beaver Valley 1. Accessed November 2026.
- NRC Beaver Valley 2. Accessed November 2026.
- NRC Susquehanna 2. Accessed November 2026.
- Shehabi, A., et al., 2024 United States Data Center Energy Usage Report, Lawrence Berkeley National Laboratory, LBNL-2001637, p. 52. Accessed October 2026.
- Oklo and Switch announcement, Dec 18, 2024 (read as a search excerpt only; the page blocked our download). Accessed November 2026.
- Nuclear News Network, deal tally (used as a cross-check only). Accessed November 2026.
Research library
More original data reports from The Uptime Report. Every report includes its methodology and a free CSV download. Browse all research
Threats and breaches
- AT&T Data Breach Settlement Payout Date
AT&T payout status, tiers, incident history - Microsoft Data Breach History
Microsoft incidents by type, 2020 to 2026 - IC3 Report 2025
IC3 losses, crime types, states per capita - AI Incidents Statistics 2026
AI incidents by year, harm type, company - Cyber Attacks 2026
Every 2026 cyber attack, primary-sourced - WordPress Vulnerabilities
WordPress plugin, theme and core CVEs - Hypervisor Vulnerabilities
Hypervisor CVEs vs exploitation - DMARC Adoption Statistics 2026
DMARC enforcement, 15,000 domains - RMM Vulnerabilities and Remote Access Flaws
RMM and remote access flaws in KEV - Identity Theft Statistics 2026
ID theft per 100K by state and type - Scam Statistics 2026
FTC fraud losses by channel and age - VPN Vulnerabilities by Vendor
VPN gateway KEV and CVEs by vendor - MFA Statistics 2026
MFA methods across 2,571 services - Password Statistics 2026
12,674 passwords tested against HIBP - Ransomware Groups 2026
Most active ransomware groups, ranked - Ransomware Statistics 2026
Leak-site victims by month since 2021 - Malicious npm Packages
Malicious npm packages, day by day - Cybersecurity Statistics 2026
70 sourced stats, every number traced - Zero-Day Statistics
Every tracked zero-day since 2014 - Phishing Statistics 2026
Four phishing measures, one evidence board - Patch Tuesday Statistics 2026
Every Microsoft CVE since 2021 - Disaster Declarations by State
FEMA data for continuity planning - Data Breach Statistics 2026
980 breaches in Have I Been Pwned - Ransomware Initial Access Vectors
CISA advisories coded by entry technique - CVE Statistics 2026
Vulnerabilities published per year, NIST NVD - How Long Do Companies Take to Report a Data Breach?
1,675 Washington notices - Known Exploited Vulnerabilities
The CISA KEV catalog analyzed - Healthcare Data Breach Report 2026
HHS OCR breach portal scorecard - Ransomware Reported to the FBI
Five-year IC3 trend
Infrastructure and uptime
- Claude Outage History
934 Claude incidents by model and hour - AMD vs Nvidia Market Share Over Time
AMD vs Nvidia share: Steam and SEC filings - iPhone Market Share by Country 2026
iPhone share in every country - Android Market Share by Version 2026
Android versions and patch status - OpenAI Outage History
1,051 OpenAI incidents, causes coded - Data Center Construction Spending 2026
Data center build spending, Census monthly - Microsoft End of Support 2026
Every 2026 Microsoft support cutoff - Fiber Internet Availability by State 2026
Fiber by state, build pace, top providers - 5G Coverage Map 2026
5G by state and carrier, FCC data - Cell Phone Outage History
FCC outages, DIRS cell sites, 911 fines - Mac Market Share 2026
Mac desktop share by country and version - Browser Market Share 2026
Browser share since 2009, by platform - Microsoft 365 Market Share 2026
Who runs email: Microsoft vs Google - CrowdStrike Outage
July 19, 2024 outage, minute by minute - Data Center Electricity Prices 2026
Power prices vs data center load, by state - Average Internet Bill 2026
Home internet prices by speed and state - Search Engine Market Share 2026
Search share since 2009, by country - ChatGPT Market Share 2026
AI chatbot referral share, every tracker - Google Cloud Outage History
Google Cloud incidents by product, 2013 on - Azure Outage History
Every Azure PIR, coded by root cause - Data Center Water Usage 2026
Water by site, company and drought - AI Energy Consumption 2026
Big Tech electricity vs US demand - SSD Prices 2026
NAND price cycle from makers’ filings - RAM Prices 2026
DRAM prices from producers’ filings - Domain Name Statistics 2026
Domains by TLD, renewals, registrars - Linux Market Share 2026
Linux desktop share, every headline traced - GitHub Outages
GitHub incidents by month since 2020 - Cloudflare Outage History
Every Cloudflare outage post-mortem - Starlink Statistics 2026
Satellites, subscribers, coverage, outages - Internet Access Statistics 2026
Home internet gaps by state and group - SQL Server End of Life
SQL Server support countdown + CVEs - Windows 11 Market Share 2026
Windows 10 vs 11 share by country - Cloud Computing Statistics 2026
Hyperscaler revenue and capex, SEC data - AWS Outage History
Every AWS Post-Event Summary since 2011 - Data Centers by State 2026
Sites, jobs, power for every state - Data Center Statistics 2026
Data center power, spending, jobs - 99.9% Uptime
Uptime calculator and 35 real SLAs - Power Outage Statistics by State
Outage hours by state, EIA data - Cost of Downtime
Revenue per hour for 3,001 public companies - Windows Server End of Life
Support dates and CVEs per server version
Regulation and disclosure
- Are Ransomware Payments Illegal? Law by Jurisdiction
Who may pay a ransom, by jurisdiction - HIPAA Security Rule Changes 2026
Security Rule status: current vs proposed - FTC Safeguards Rule Breach Notification
500-consumer, 30-day FTC breach duty - Data Center Moratorium by State 2026
Moratoria and bans in every state - State Privacy Laws 2026
23 state privacy laws, compared - State AI Laws 2026
131 state AI laws, dates and penalties - FedRAMP Statistics 2026
FedRAMP authorizations, GSA data - Item 1C Cybersecurity Disclosures
What 600 10-Ks say in Item 1C - CMMC Certification Statistics 2026
CMMC demand vs assessor capacity - Data Brokers List 2026
728 brokers across three state registries - SEC Cybersecurity Incident Disclosures
Every 8-K Item 1.05 filing - HIPAA Enforcement Tracker
Every OCR penalty and settlement
Workforce and pay
- Intel Layoff Tracker
Every Intel WARN notice, by site and date - Amazon Layoffs by State
Amazon WARN notices, state by state - Oracle Layoffs by State
Oracle WARN notices and restructuring cost - Cloud Architect vs Cloud Engineer Salary
Architect vs engineer pay, H-1B filings - Entry Level DevOps Engineer Salary
Entry level DevOps pay, H-1B filings - Microsoft Layoff History Timeline
Every round dated, 2009 to 2026 - Google Layoffs by Year
Notices, headcount, severance by year - AI Engineer vs ML Engineer Salary
AI vs ML engineer pay, from H-1B filings - Data Engineer Salary by Experience
Data engineer pay by DOL wage level - Most Popular Programming Languages 2026
Language ranks by country, GitHub data - Computer Science Graduates Per Year
CS degrees per year, IPEDS 2011 to 2024 - Data Scientist Salary 2026
Data scientist pay ladder and metros, BLS - Web Developer Salary 2026
Web dev vs software pay by state, BLS - AI at Work Statistics 2026
Worker AI use: ever, weekly, daily, by job - Network Engineer Salary 2026
Network engineer vs admin pay, BLS - IT Manager Salary 2026
IT manager pay by industry, BLS OEWS - Software Engineer Salary 2026
Developer pay by metro, BLS OEWS - H-1B Statistics 2026
H-1B lottery, employers, and wages - AI Layoffs 2026
AI-blamed job cuts, sourced to filings - Help Desk Salary 2026
Help desk hourly pay, BLS OEWS - Cybersecurity Salary 2026
Security pay percentiles, BLS OEWS - Women in Tech Statistics 2026
Women’s share of tech jobs since 2011 - IT Unemployment Rate 2026
Tech vs national jobless rate, monthly - Tech Job Postings 2026
Tech postings vs 2020, by role and country - Tech Layoffs 2026
Tech layoffs from state WARN notices - Remote Work Statistics 2026
Telework by job, industry, and state - Highest Paying Cities for IT Jobs 2026
Metro pay by role, BLS OEWS - The Tech Job Market in 2026
Openings, quits, hires, layoffs - IT Salaries by State 2026
Pay matrix for four IT roles - IT and Cybersecurity Jobs Outlook 2026
BLS employment projections
MSP market and spending
- AI Capex 2026
Big Tech capex vs cash flow, SEC data - Cybersecurity Budget 2027
Federal and CISA cyber budgets, benchmarks - Microsoft 365 Price Increase 2026
Every M365 price change, vs inflation - Computer Prices 2026
Computer price indexes and HS 8471 imports - MSP Market Size 2026
Managed services market, built from Census - Small Business AI Adoption 2026
AI use by firm size, sector, state, Census - Cyber Insurance Statistics
Cyber insurance market, NAIC 2015-2024 - IT Spending by Industry
IT investment by industry, BEA - IT Services Industry Growth 2026
Census revenue by service industry - IT Hourly Rates 2026
Hourly IT labor rates, GSA contracts - VoIP Statistics 2026
Business VoIP vs landlines, FCC - MSP Industry Statistics 2026
Jobs, wages, and firms, BLS QCEW - Federal IT Spending 2026
IT services contracts, USAspending - IT Services Firms by State
Census business patterns atlas
Leave a Reply